Marton - Complete - Circa 100k
Demolition of internal walls and removal of existing floors
Installation of circa 2.2tonne of Steelwork
Install of new concrete slabs
Install of Underfloor Heating
Install of Bi Folds Doors and Windows
Install of 4 Nr Veluxs
Kitchen to suit revised layout with Lily Ann Interiors